Connect with us

Phase 1: March 8 Update

Featured

Phase 1: March 8 Update

Phase 1: March 8 Update

Exciting new enhancements continue along the Mangrove Walk.  This week, the team is finishing the rubber surfacing on the eastern half of the Mangrove Walk and into the hammock area. Landscape contractors are also on-site doing both preparatory work and grading to continue to install new landscaping. Over the next two weeks, deck contractors are also beginning to put down the etched Kebony wood in the deck locations.

In addition to some finishing work along the Mangrove Walk, the relocation of the five green buttonwood trees to the eastern area of the site will be finalized.

The walkway that connects the north entrance of the Mangrove Bayou Bridge is now reopened after the construction team began laying the surfacing on the eastern portion of the walkway. Please continue to reference our current walking map for easy accessibility. 

More in Featured

Leadership

655 North Tamiami Trail, Sarasota, FL 34236

Phone:  (941) 203-5316

Press & Media


Nicole Zimmerman

[email protected]

(941) 365-9200

General Inquiries

Lori Denny

[email protected]

(941) 203-5316

To Top
X