Phase 1: May 16 Update

Construction

Phase 1: May 16 Update

Phase 1: May 16 Update

This week, the construction team has made continued progress on the site’s temporary walking paths.

A new sidewalk was installed by the Blue Pagoda (The Bay Offices) to create a connection between the parking lot and Van Wezel Way.

Looking ahead to next week, wayfinding signage will be installed along the temporary walking paths to help visitors easily navigate the site during daily walks or runs.

More in Construction

  • Construction

    Phase 1: September 12 Update

    By

    Bill Waddill, Chief Implementation Officer at The Bay Park Conservancy, gives a progress update on the...

  • Construction

    Phase 1: August 22 Update

    By

    The Mangrove Walk continues to take shape! In recent days, concrete was poured for the walking...

  • Construction

    Phase 1: July 27 Update

    By

    As construction of Phase 1 continues, visitors to The Bay may notice the removal of some...

  • Construction

    Phase 1: July 20 Update

    By

    Our construction team started to pour the concrete for the sidewalk and walking path for the Mangrove Walk. ...

  • Construction

    Phase 1: July 13 Update

    By

    This week, within the confines of the construction site, non-native and exotic trees were removed in preparation to...

Location

655 North Tamiami Trail, Sarasota, FL 34236

Phone:  (941) 203-5316

Press & Media


Heather McLain

[email protected]

(941) 365-9200

General Inquiries

Lori Denny

[email protected]

(941) 203-5316

To Top

Sign up for our newsletter